PETRA III Beamtime Schedule 2021

Revision: 02-Aug-2021

Beamtime schedule for beamline P01


StartEnd 
15-Mar-2021 24-Mar-2021 Max-Planck-Society Research
25-Mar-2021 02-Apr-2021 Max-Planck-Society Research
12-Apr-2021 13-Apr-2021 Commissioning/Technical Development
13-Apr-2021 17-Apr-2021 Xu
17-Apr-2021 21-Apr-2021 Hermann
22-Apr-2021 24-Apr-2021 Commissioning/Technical Development
24-Apr-2021 28-Apr-2021 Kramm/Heppe
29-Apr-2021 04-May-2021 Kumar
04-May-2021 05-May-2021 Commissioning/Technical Development
06-May-2021 10-May-2021 Evers
10-May-2021 11-May-2021 Commissioning/Technical Development
11-May-2021 17-May-2021 Roehlsberger/Schulze
27-May-2021 01-Jun-2021 In-House Research
01-Jun-2021 04-Jun-2021 Crespo Lopez-Urrutia/Bernitt
04-Jun-2021 09-Jun-2021 Temst
10-Jun-2021 16-Jun-2021 Ovchinnikov/Kazak
17-Jun-2021 23-Jun-2021 Max-Planck-Society Research
24-Jun-2021 30-Jun-2021 Max-Planck-Society Research
01-Jul-2021 07-Jul-2021 In-House Research
04-Aug-2021 07-Aug-2021 In-House Research
07-Aug-2021 14-Aug-2021 Lauterbach
14-Aug-2021 15-Aug-2021 Commissioning/Technical Development
15-Aug-2021 18-Aug-2021 Reddy
19-Aug-2021 25-Aug-2021 Roehlsberger/Negi
26-Aug-2021 30-Aug-2021 Schuenemann
06-Sep-2021 15-Sep-2021 Max-Planck-Society Research
16-Sep-2021 21-Sep-2021 Dominko/Kavcic
21-Sep-2021 22-Sep-2021 In-House Research
23-Sep-2021 29-Sep-2021 Ngene
30-Sep-2021 06-Oct-2021 Max-Planck-Society Research
07-Oct-2021 11-Oct-2021 Max-Planck-Society Research
18-Oct-2021 23-Oct-2021 Schuenemann
23-Oct-2021 29-Oct-2021 Roehlsberger/Bocklage
29-Oct-2021 03-Nov-2021 Caserta
04-Nov-2021 10-Nov-2021 Kupenko
11-Nov-2021 17-Nov-2021 In-House Research
22-Nov-2021 29-Nov-2021 Max-Planck-Society Research
29-Nov-2021 01-Dec-2021 Max-Planck-Society Research
02-Dec-2021 08-Dec-2021 Max-Planck-Society Research
09-Dec-2021 14-Dec-2021 Max-Planck-Society Research
14-Dec-2021 15-Dec-2021 Wilson/Hendler Avidor
16-Dec-2021 22-Dec-2021 Max-Planck-Society Research

Beamtime schedule for beamline P02.1


StartEnd 
15-Mar-2021 18-Mar-2021 Skjaervoe/Jensen
18-Mar-2021 22-Mar-2021 Bette/Gallo
25-Mar-2021 29-Mar-2021 Song/Shen
29-Mar-2021 02-Apr-2021 Commissioning/Technical Development
13-Apr-2021 15-Apr-2021 Hernandez
15-Apr-2021 21-Apr-2021 Weidenthaler
22-Apr-2021 24-Apr-2021 Commissioning/Technical Development
24-Apr-2021 05-May-2021 In-House Research
06-May-2021 10-May-2021 Froeba/Lehmkuehler
10-May-2021 14-May-2021 Hinterstein/Kodumudi Venkataraman
14-May-2021 17-May-2021 Jensen
27-May-2021 31-May-2021 Henke
31-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 03-Jun-2021 Rapid Access
03-Jun-2021 03-Jun-2021 Rapid Access
03-Jun-2021 03-Jun-2021 Rapid Access
03-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 04-Jun-2021 Rapid Access
04-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 05-Jun-2021 Rapid Access
05-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 06-Jun-2021 Rapid Access
06-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 07-Jun-2021 Rapid Access
07-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 08-Jun-2021 Rapid Access
08-Jun-2021 09-Jun-2021 Rapid Access
09-Jun-2021 09-Jun-2021 Rapid Access
10-Jun-2021 10-Jun-2021 Commissioning/Technical Development
11-Jun-2021 12-Jun-2021 Commissioning/Technical Development
14-Jun-2021 16-Jun-2021 Grunwaldt/Klag
17-Jun-2021 21-Jun-2021 Biswas
21-Jun-2021 23-Jun-2021 Wuttig/Wei
24-Jun-2021 27-Jun-2021 Graetz
27-Jun-2021 28-Jun-2021 Bo/Jaschin
28-Jun-2021 02-Jul-2021 Norby
02-Jul-2021 05-Jul-2021 Commissioning/Technical Development
05-Jul-2021 06-Jul-2021 Lock
06-Jul-2021 07-Jul-2021 In-House Research
04-Aug-2021 06-Aug-2021 Brant
06-Aug-2021 09-Aug-2021 Fedotov
09-Aug-2021 11-Aug-2021 Kieslich
13-Aug-2021 16-Aug-2021 Commissioning/Technical Development
16-Aug-2021 20-Aug-2021 Henke
20-Aug-2021 23-Aug-2021 Zobel/Prinz
23-Aug-2021 25-Aug-2021 Christensen/Shyam
26-Aug-2021 29-Aug-2021 Koruza
06-Sep-2021 10-Sep-2021 In-House Research
10-Sep-2021 15-Sep-2021 In-House Research
16-Sep-2021 20-Sep-2021 Knapp/Hua
20-Sep-2021 22-Sep-2021 Mikhailova/Gorbunov
23-Sep-2021 25-Sep-2021 Hansen/Knapp
25-Sep-2021 27-Sep-2021 Hansen/Hansen
27-Sep-2021 28-Sep-2021 Madsen/Rades
04-Oct-2021 06-Oct-2021 Schroeder
07-Oct-2021 11-Oct-2021 Senyshyn
18-Oct-2021 22-Oct-2021 Sahlberg/Ek
22-Oct-2021 26-Oct-2021 Bomholdt Ravnsbaek
28-Oct-2021 31-Oct-2021 Pistidda/Le
31-Oct-2021 03-Nov-2021 Jensen/Juelsholt
08-Nov-2021 10-Nov-2021 Wei
11-Nov-2021 17-Nov-2021 Weidenthaler
23-Nov-2021 26-Nov-2021 Weidenthaler
09-Dec-2021 13-Dec-2021 Topwal
13-Dec-2021 17-Dec-2021 Senguttuvan

Beamtime schedule for beamline P02.2


StartEnd 
15-Mar-2021 16-Mar-2021 Management Contingency
16-Mar-2021 17-Mar-2021 Commissioning/Technical Development
17-Mar-2021 19-Mar-2021 Commissioning/Technical Development
19-Mar-2021 22-Mar-2021 Rashchenko/Romanenko
22-Mar-2021 26-Mar-2021 Giordano
26-Mar-2021 29-Mar-2021 Comodi
29-Mar-2021 01-Apr-2021 Rashchenko
01-Apr-2021 02-Apr-2021 In-House Research
13-Apr-2021 15-Apr-2021 Dubrovinsky/Meier
15-Apr-2021 17-Apr-2021 Struzhkin/Troyan
17-Apr-2021 19-Apr-2021 Dalladay-Simpson/Edmund
19-Apr-2021 21-Apr-2021 Mukherjee
22-Apr-2021 25-Apr-2021 Mcmahon
25-Apr-2021 26-Apr-2021 In-House Research
26-Apr-2021 28-Apr-2021 Reddy
29-Apr-2021 01-May-2021 Commissioning/Technical Development
01-May-2021 03-May-2021 Winkler/Binck
03-May-2021 05-May-2021 Ghosh
06-May-2021 07-May-2021 Commissioning/Technical Development
07-May-2021 09-May-2021 Tsirlin
09-May-2021 10-May-2021 In-House Research
10-May-2021 13-May-2021 Gorelli
13-May-2021 14-May-2021 In-House Research
14-May-2021 15-May-2021 In-House Research
15-May-2021 17-May-2021 In-House Research
27-May-2021 29-May-2021 Mcmahon
29-May-2021 31-May-2021 In-House Research
31-May-2021 02-Jun-2021 Dubrovinsky/Khandarkhaeva
03-Jun-2021 04-Jun-2021 Commissioning/Technical Development
04-Jun-2021 05-Jun-2021 In-House Research
05-Jun-2021 07-Jun-2021 Lobanov/Schifferle
07-Jun-2021 08-Jun-2021 Commissioning/Technical Development
08-Jun-2021 12-Jun-2021 Evans/Jenei
12-Jun-2021 14-Jun-2021 In-House Research
14-Jun-2021 19-Jun-2021 Marquardt
19-Jun-2021 20-Jun-2021 In-House Research
20-Jun-2021 23-Jun-2021 Antonangeli/Siersch
24-Jun-2021 25-Jun-2021 Commissioning/Technical Development
25-Jun-2021 28-Jun-2021 Evans/Jenei
28-Jun-2021 29-Jun-2021 Commissioning/Technical Development
29-Jun-2021 30-Jun-2021 Lee
01-Jul-2021 03-Jul-2021 Lee
03-Jul-2021 07-Jul-2021 Sanchez-Valle
04-Aug-2021 07-Aug-2021 Wilke/Libon
07-Aug-2021 09-Aug-2021 Ma/Liu
09-Aug-2021 11-Aug-2021 Salke
12-Aug-2021 14-Aug-2021 Krivovichev/Gorelova
14-Aug-2021 16-Aug-2021 Kim
16-Aug-2021 18-Aug-2021 Winkler/Lkhamsuren
19-Aug-2021 20-Aug-2021 Commissioning/Technical Development
20-Aug-2021 23-Aug-2021 Evans/Jenei
23-Aug-2021 25-Aug-2021 Lazor
26-Aug-2021 27-Aug-2021 In-House Research
27-Aug-2021 30-Aug-2021 Marquardt
06-Sep-2021 09-Sep-2021 Sanloup/Chen
09-Sep-2021 11-Sep-2021 In-House Research
11-Sep-2021 12-Sep-2021 In-House Research
12-Sep-2021 14-Sep-2021 In-House Research
14-Sep-2021 18-Sep-2021 Boffa Ballaran/Criniti
18-Sep-2021 19-Sep-2021 In-House Research
19-Sep-2021 20-Sep-2021 In-House Research
20-Sep-2021 22-Sep-2021 Commissioning/Technical Development
23-Sep-2021 26-Sep-2021 Colliander
26-Sep-2021 29-Sep-2021 Sood/Dharmaraj
30-Sep-2021 03-Oct-2021 Duffy
03-Oct-2021 06-Oct-2021 Dattelbaum/Sturtevant
07-Oct-2021 08-Oct-2021 Commissioning/Technical Development
08-Oct-2021 11-Oct-2021 Lee
18-Oct-2021 19-Oct-2021 Commissioning/Technical Development
19-Oct-2021 22-Oct-2021 Evans/Jenei
22-Oct-2021 23-Oct-2021 McMahon/Husband
23-Oct-2021 24-Oct-2021 Prescher
24-Oct-2021 25-Oct-2021 Liermann/Jenei
25-Oct-2021 26-Oct-2021 Commissioning/Technical Development
26-Oct-2021 30-Oct-2021 Bykova
30-Oct-2021 02-Nov-2021 Dubrovinsky/Aslandukova
02-Nov-2021 05-Nov-2021 Lee
05-Nov-2021 07-Nov-2021 Friedemann
07-Nov-2021 10-Nov-2021 Kupenko/Kolesnikov
11-Nov-2021 13-Nov-2021 Commissioning/Technical Development
13-Nov-2021 15-Nov-2021 In-House Research
15-Nov-2021 16-Nov-2021 Liermann/Jenei
16-Nov-2021 17-Nov-2021 Prescher
22-Nov-2021 24-Nov-2021 Mcmahon
24-Nov-2021 28-Nov-2021 Ji
28-Nov-2021 01-Dec-2021 Mcmahon
02-Dec-2021 04-Dec-2021 Trautmann/Tzifas
04-Dec-2021 06-Dec-2021 Rashchenko/Semerikova
06-Dec-2021 08-Dec-2021 Serghiou
09-Dec-2021 11-Dec-2021 Bykov
11-Dec-2021 12-Dec-2021 McMahon/Husband
12-Dec-2021 13-Dec-2021 In-House Research
13-Dec-2021 15-Dec-2021 Sanchez-Valle/Mondal
16-Dec-2021 18-Dec-2021 Komabayashi
18-Dec-2021 20-Dec-2021 Mcmahon
20-Dec-2021 22-Dec-2021 Britvin/Gorelova

Beamtime schedule for beamline P03


StartEnd 
20-Mar-2021 27-Mar-2021 Keckes
27-Mar-2021 30-Mar-2021 Schneider/Holzapfel
13-Apr-2021 15-Apr-2021 Management Contingency
16-Apr-2021 20-Apr-2021 Soederberg/Brett
20-Apr-2021 26-Apr-2021 Mueller-Buschbaum
26-Apr-2021 28-Apr-2021 Ma
29-Apr-2021 04-May-2021 Andreasen/Soerensen
04-May-2021 08-May-2021 Mascotto
08-May-2021 12-May-2021 Commissioning/Technical Development
12-May-2021 14-May-2021 Ruebhausen/Glier
14-May-2021 17-May-2021 Ruebhausen/Akinsinde
27-May-2021 01-Jun-2021 Koyiloth Vayalil
01-Jun-2021 02-Jun-2021 In-House Research
03-Jun-2021 04-Jun-2021 In-House Research
04-Jun-2021 05-Jun-2021 In-House Research
05-Jun-2021 07-Jun-2021 In-House Research
07-Jun-2021 11-Jun-2021 Zhang
11-Jun-2021 16-Jun-2021 Mueller-Buschbaum
17-Jun-2021 18-Jun-2021 Commissioning/Technical Development
18-Jun-2021 21-Jun-2021 Yu/Stormvinter
21-Jun-2021 26-Jun-2021 Wagermaier
26-Jun-2021 30-Jun-2021 Comelli/Ghirardello
01-Jul-2021 06-Jul-2021 Andreasen
06-Jul-2021 07-Jul-2021 In-House Research
04-Aug-2021 09-Aug-2021 Davydok
09-Aug-2021 14-Aug-2021 Schneider
14-Aug-2021 18-Aug-2021 Techert/Erbes
19-Aug-2021 22-Aug-2021 Roth/Harder
22-Aug-2021 23-Aug-2021 Roth/Chen
24-Aug-2021 30-Aug-2021 Szyszka/Haertel
06-Sep-2021 08-Sep-2021 Industry
08-Sep-2021 10-Sep-2021 Wieland/Iskhakova
10-Sep-2021 15-Sep-2021 Mueller-Buschbaum
16-Sep-2021 20-Sep-2021 Ma
20-Sep-2021 24-Sep-2021 Mannsfeld
25-Sep-2021 29-Sep-2021 Lindbergh/Gratrex
30-Sep-2021 05-Oct-2021 Jaehn/Fiedler
05-Oct-2021 08-Oct-2021 Baecke
08-Oct-2021 11-Oct-2021 Johansson
18-Oct-2021 20-Oct-2021 Education
20-Oct-2021 23-Oct-2021 Kabiraj/Jatav
23-Oct-2021 27-Oct-2021 Schreiber/Hinderhofer
28-Oct-2021 29-Oct-2021 Noei
29-Oct-2021 01-Nov-2021 Rosen
01-Nov-2021 05-Nov-2021 Lendel/Herneke
05-Nov-2021 09-Nov-2021 Schneider
11-Nov-2021 15-Nov-2021 Hammer/vom Scheidt
15-Nov-2021 17-Nov-2021 Johansson/Ribca
22-Nov-2021 25-Nov-2021 Roth/Gensch
25-Nov-2021 30-Nov-2021 Kumar
02-Dec-2021 03-Dec-2021 Malmstroem/Alexakis
04-Dec-2021 08-Dec-2021 Duarte Correa
09-Dec-2021 13-Dec-2021 Grigorian
13-Dec-2021 17-Dec-2021 Busse/Woelfel
17-Dec-2021 22-Dec-2021 Fleck

Beamtime schedule for beamline P04


StartEnd 
21-Mar-2021 23-Mar-2021 In-House Research
23-Mar-2021 24-Mar-2021 Commissioning/Technical Development
25-Mar-2021 31-Mar-2021 Bentmann
31-Mar-2021 02-Apr-2021 Kohlstedt/Petraru
13-Apr-2021 15-Apr-2021 Martins
15-Apr-2021 17-Apr-2021 Commissioning/Technical Development
17-Apr-2021 20-Apr-2021 Pfau
20-Apr-2021 21-Apr-2021 In-House Research
22-Apr-2021 28-Apr-2021 Rossnagel/Kallaene
29-Apr-2021 30-Apr-2021 Commissioning/Technical Development
30-Apr-2021 05-May-2021 Ludwig/Luehl
06-May-2021 10-May-2021 Giri
10-May-2021 14-May-2021 Gruebel/Philippi-Kobs
14-May-2021 17-May-2021 Ludwig/Luehl
27-May-2021 28-May-2021 In-House Research
28-May-2021 07-Jun-2021 Schoeffler/Jahnke
07-Jun-2021 08-Jun-2021 Commissioning/Technical Development
12-Jun-2021 13-Jun-2021 Iwasawa/Hoesch
13-Jun-2021 16-Jun-2021 Iwasawa/Hoesch
17-Jun-2021 21-Jun-2021 Beye/Schunck
22-Jun-2021 23-Jun-2021 Eusterhues/Haidl
24-Jun-2021 29-Jun-2021 Eusterhues/Haidl
29-Jun-2021 30-Jun-2021 Commissioning/Technical Development
01-Jul-2021 07-Jul-2021 Buhr/Schippers
06-Aug-2021 10-Aug-2021 In-House Research
10-Aug-2021 12-Aug-2021 In-House Research
12-Aug-2021 14-Aug-2021 Commissioning/Technical Development
14-Aug-2021 22-Aug-2021 Commissioning/Technical Development
23-Aug-2021 30-Aug-2021 Hans/Bloss
10-Sep-2021 12-Sep-2021 Kohlstedt/Petraru
12-Sep-2021 14-Sep-2021 Kohlstedt/Zahari
14-Sep-2021 15-Sep-2021 Gruebel/Marotzke
16-Sep-2021 22-Sep-2021 Schlathoelter/Poully
23-Sep-2021 29-Sep-2021 Crespo Lopez-Urrutia/Kuehn
30-Sep-2021 06-Oct-2021 Martins/Nissen
19-Oct-2021 22-Oct-2021 Gruebel/Marotzke
28-Oct-2021 03-Nov-2021 Bentmann
04-Nov-2021 10-Nov-2021 Schoenhense/Elmers
11-Nov-2021 17-Nov-2021 Rossnagel/Bentmann
25-Nov-2021 01-Dec-2021 Seidel/Hein
02-Dec-2021 08-Dec-2021 Beye
09-Dec-2021 15-Dec-2021 Eusterhues/Haidl
16-Dec-2021 22-Dec-2021 Yin/Goy

Beamtime schedule for beamline P05


StartEnd 
18-Mar-2021 22-Mar-2021 In-House Research
22-Mar-2021 24-Mar-2021 Krause/Nopens
25-Mar-2021 28-Mar-2021 Soederberg/Gordeyeva
28-Mar-2021 29-Mar-2021 Soederberg/Gordeyeva
30-Mar-2021 02-Apr-2021 Main
12-Apr-2021 15-Apr-2021 Herzen
15-Apr-2021 19-Apr-2021 Bugelnig
19-Apr-2021 21-Apr-2021 In-House Research
22-Apr-2021 26-Apr-2021 Gibmeier
26-Apr-2021 28-Apr-2021 Commissioning/Technical Development
29-Apr-2021 03-May-2021 Ras/Hammel
03-May-2021 05-May-2021 Roeder
06-May-2021 10-May-2021 Sierra Lopez/Maugeri
10-May-2021 12-May-2021 Thyrel
14-May-2021 17-May-2021 Herzen
27-May-2021 28-May-2021 In-House Research
28-May-2021 31-May-2021 Commissioning/Technical Development
31-May-2021 02-Jun-2021 Bukreeva/Fratini
03-Jun-2021 09-Jun-2021 Moosmann/Galli
10-Jun-2021 11-Jun-2021 In-House Research
11-Jun-2021 16-Jun-2021 Hammel/Naumann
17-Jun-2021 20-Jun-2021 In-House Research
20-Jun-2021 23-Jun-2021 Saranathan
24-Jun-2021 28-Jun-2021 Grunwaldt/Pashminehazar
28-Jun-2021 30-Jun-2021 Keckes
01-Jul-2021 07-Jul-2021 Zeller-Plumhoff
04-Aug-2021 11-Aug-2021 Commissioning/Technical Development
12-Aug-2021 15-Aug-2021 Wipfler/Hammel
15-Aug-2021 18-Aug-2021 Wipfler/Hammel
19-Aug-2021 23-Aug-2021 Gibmeier
23-Aug-2021 25-Aug-2021 Hecht/Serefoglu
26-Aug-2021 30-Aug-2021 Hammel/Henne
10-Sep-2021 15-Sep-2021 Merk
16-Sep-2021 20-Sep-2021 Saltin
20-Sep-2021 22-Sep-2021 Krause/Nopens
23-Sep-2021 27-Sep-2021 Liotti/HAN
01-Oct-2021 04-Oct-2021 Kuo
04-Oct-2021 08-Oct-2021 Wipfler/Hammel
08-Oct-2021 11-Oct-2021 Wipfler/Hammel
18-Oct-2021 22-Oct-2021 Herzen
22-Oct-2021 26-Oct-2021 Manke/SUN
29-Oct-2021 01-Nov-2021 Zeller-Plumhoff/Menze
01-Nov-2021 05-Nov-2021 Hammel/Naumann
05-Nov-2021 08-Nov-2021 Herzen
12-Nov-2021 15-Nov-2021 Wieland
15-Nov-2021 17-Nov-2021 Peth/Felde
26-Nov-2021 29-Nov-2021 Zeller-Plumhoff/Espiritu
29-Nov-2021 01-Dec-2021 Bekes
02-Dec-2021 06-Dec-2021 Krause/Nopens
06-Dec-2021 10-Dec-2021 Konchakova
10-Dec-2021 15-Dec-2021 Busse/Stockhausen
16-Dec-2021 22-Dec-2021 Zeller-Plumhoff

Beamtime schedule for beamline P06


StartEnd 
15-Mar-2021 22-Mar-2021 Schroer/Schropp
22-Mar-2021 27-Mar-2021 Schroer/Seiboth
27-Mar-2021 02-Apr-2021 Kahnt
15-Apr-2021 19-Apr-2021 Modregger
19-Apr-2021 23-Apr-2021 In-House Research
23-Apr-2021 25-Apr-2021 In-House Research
29-Apr-2021 05-May-2021 Monico/Moretti
06-May-2021 08-May-2021 In-House Research
08-May-2021 11-May-2021 Commissioning/Technical Development
11-May-2021 17-May-2021 In-House Research
27-May-2021 31-May-2021 In-House Research
31-May-2021 02-Jun-2021 Commissioning/Technical Development
03-Jun-2021 07-Jun-2021 Lotze/Kalbfleisch
07-Jun-2021 08-Jun-2021 Commissioning/Technical Development
08-Jun-2021 14-Jun-2021 Grunwaldt/Sheppard
14-Jun-2021 19-Jun-2021 Kuepper/Morina
19-Jun-2021 25-Jun-2021 Rumancev
25-Jun-2021 28-Jun-2021 Kolbe
28-Jun-2021 28-Jun-2021 Commissioning/Technical Development
28-Jun-2021 01-Jul-2021 Commissioning/Technical Development
01-Jul-2021 07-Jul-2021 Grunwaldt/Sheppard
04-Aug-2021 07-Aug-2021 Sanyal
07-Aug-2021 11-Aug-2021 Wallentin
12-Aug-2021 18-Aug-2021 Vincze/Brenker
19-Aug-2021 23-Aug-2021 Fittschen/Hampel
26-Aug-2021 30-Aug-2021 Commissioning/Technical Development
07-Sep-2021 13-Sep-2021 Keune/Broers
13-Sep-2021 20-Sep-2021 Janssens
20-Sep-2021 27-Sep-2021 Bulin
27-Sep-2021 04-Oct-2021 Garrevoet/Le Cabec
22-Oct-2021 25-Oct-2021 Blaudez
25-Oct-2021 01-Nov-2021 Rosenhahn
04-Nov-2021 09-Nov-2021 Vincze/Brenker
09-Nov-2021 15-Nov-2021 Bekes
22-Nov-2021 27-Nov-2021 Vila-Comamala
27-Nov-2021 04-Dec-2021 Vogt/Schropp
05-Dec-2021 10-Dec-2021 Huber
10-Dec-2021 17-Dec-2021 Hill/Driscoll
17-Dec-2021 22-Dec-2021 Grunwaldt/Sheppard

Beamtime schedule for beamline P07


StartEnd 
16-Mar-2021 18-Mar-2021 In-House Research
18-Mar-2021 21-Mar-2021 Epp/Meyer
21-Mar-2021 24-Mar-2021 Reimers/Poeche
25-Mar-2021 30-Mar-2021 Devaraj
31-Mar-2021 02-Apr-2021 In-House Research
12-Apr-2021 14-Apr-2021 Commissioning/Technical Development
14-Apr-2021 17-Apr-2021 In-House Research
17-Apr-2021 21-Apr-2021 Mandal
22-Apr-2021 25-Apr-2021 In-House Research
25-Apr-2021 27-Apr-2021 In-House Research
27-Apr-2021 28-Apr-2021 In-House Research
29-Apr-2021 30-Apr-2021 Siemers
30-Apr-2021 02-May-2021 Siemers
02-May-2021 04-May-2021 In-House Research
04-May-2021 05-May-2021 Industry
06-May-2021 08-May-2021 Commissioning/Technical Development
08-May-2021 10-May-2021 In-House Research
10-May-2021 13-May-2021 In-House Research
13-May-2021 17-May-2021 In-House Research
03-Jun-2021 03-Jun-2021 Industry
04-Jun-2021 07-Jun-2021 Sokolowski-Tinten/Zalden
10-Jun-2021 13-Jun-2021 Koerner
13-Jun-2021 16-Jun-2021 Staron/Rosigkeit
17-Jun-2021 17-Jun-2021 Industry
17-Jun-2021 18-Jun-2021 Commissioning/Technical Development
18-Jun-2021 23-Jun-2021 Le Cabec/Power
24-Jun-2021 28-Jun-2021 Herzen/Riedel
28-Jun-2021 30-Jun-2021 Herzen/Taphorn
01-Jul-2021 02-Jul-2021 Commissioning/Technical Development
02-Jul-2021 05-Jul-2021 In-House Research
05-Jul-2021 07-Jul-2021 Commissioning/Technical Development
08-Aug-2021 10-Aug-2021 Koziej/Nickel
10-Aug-2021 11-Aug-2021 In-House Research
12-Aug-2021 18-Aug-2021 Birch/Nayak
19-Aug-2021 24-Aug-2021 Klemeyer
24-Aug-2021 24-Aug-2021 In-House Research
24-Aug-2021 27-Aug-2021 Pyczak/Liang
27-Aug-2021 30-Aug-2021 Epp/Tapar
09-Sep-2021 13-Sep-2021 In-House Research
13-Sep-2021 15-Sep-2021 In-House Research
16-Sep-2021 19-Sep-2021 Mayer/Musi
19-Sep-2021 22-Sep-2021 Spoerk-Erdely/Graf
23-Sep-2021 27-Sep-2021 Milatz
30-Sep-2021 04-Oct-2021 Sheppard/Das
19-Oct-2021 23-Oct-2021 Barriobero Vila
23-Oct-2021 25-Oct-2021 Maawad
25-Oct-2021 27-Oct-2021 Gilles/Kuemmel
30-Oct-2021 01-Nov-2021 Staron/Henninger
01-Nov-2021 03-Nov-2021 Zenk
04-Nov-2021 10-Nov-2021 Koziej/Nickel
12-Nov-2021 17-Nov-2021 Keckes
23-Nov-2021 29-Nov-2021 Herzen
02-Dec-2021 08-Dec-2021 Wieland/Iskhakova
16-Dec-2021 22-Dec-2021 Merte

Beamtime schedule for beamline P08


StartEnd 
15-Mar-2021 17-Mar-2021 Xu
18-Mar-2021 22-Mar-2021 Schreiber/Gerlach
22-Mar-2021 24-Mar-2021 Fechtelkord
25-Mar-2021 28-Mar-2021 Tolan/Moron
28-Mar-2021 30-Mar-2021 In-House Research
30-Mar-2021 02-Apr-2021 Pusterla/Schneck
12-Apr-2021 21-Apr-2021 Magnussen/Murphy
22-Apr-2021 26-Apr-2021 Fleig/Nenning
26-Apr-2021 28-Apr-2021 Roth/Sohn
29-Apr-2021 03-May-2021 Schreiber/Hinderhofer
03-May-2021 08-May-2021 Mascotto
08-May-2021 11-May-2021 Hofmann/Gostkowska-Lekner
12-May-2021 17-May-2021 Unruh/Prihoda
27-May-2021 01-Jun-2021 Chung/Stierle
03-Jun-2021 09-Jun-2021 In-House Research
10-Jun-2021 15-Jun-2021 Pietsch/Al Hassan
17-Jun-2021 21-Jun-2021 Cornelius
21-Jun-2021 30-Jun-2021 In-House Research
01-Jul-2021 05-Jul-2021 Schreiber/Gerlach
05-Jul-2021 07-Jul-2021 Commissioning/Technical Development
07-Aug-2021 11-Aug-2021 In-House Research
12-Aug-2021 16-Aug-2021 Avasthi/sharma
16-Aug-2021 18-Aug-2021 Wollschlaeger
19-Aug-2021 22-Aug-2021 Huber/May
26-Aug-2021 30-Aug-2021 Saha
10-Sep-2021 13-Sep-2021 Unruh/Goetz
13-Sep-2021 15-Sep-2021 Hanke
17-Sep-2021 20-Sep-2021 Brezesinski/Fritz
21-Sep-2021 22-Sep-2021 Commissioning/Technical Development
23-Sep-2021 29-Sep-2021 Maldonado
30-Sep-2021 06-Oct-2021 Harvey/Woelk
07-Oct-2021 11-Oct-2021 Schreiber/Hinderhofer
21-Oct-2021 27-Oct-2021 Murphy/Magnussen
04-Nov-2021 08-Nov-2021 Busch/Huber
08-Nov-2021 10-Nov-2021 Huber/Vincent
11-Nov-2021 17-Nov-2021 Sobierajski/Antonowicz
22-Nov-2021 25-Nov-2021 Fox/Lu
25-Nov-2021 28-Nov-2021 Brezesinski/Strati
28-Nov-2021 01-Dec-2021 Brezesinski/Sturm
02-Dec-2021 07-Dec-2021 Mukhopadhyay
09-Dec-2021 13-Dec-2021 Mascotto
13-Dec-2021 18-Dec-2021 Schreiber/Gerlach

Beamtime schedule for beamline P09


StartEnd 
15-Mar-2021 16-Mar-2021 Matzenbacher Bittar/Linares Mardegan
16-Mar-2021 19-Mar-2021 Nair
19-Mar-2021 24-Mar-2021 Borgatti
25-Mar-2021 29-Mar-2021 Hu
29-Mar-2021 30-Mar-2021 Matzenbacher Bittar/Linares Mardegan
30-Mar-2021 01-Apr-2021 Nair
12-Apr-2021 14-Apr-2021 Commissioning/Technical Development
14-Apr-2021 16-Apr-2021 Hu
16-Apr-2021 19-Apr-2021 Commissioning/Technical Development
19-Apr-2021 21-Apr-2021 Commissioning/Technical Development
22-Apr-2021 03-May-2021 Yuan/Xie
03-May-2021 07-May-2021 Commissioning/Technical Development
07-May-2021 11-May-2021 Rubensson/Ghosh
11-May-2021 17-May-2021 Kuschel
27-May-2021 02-Jun-2021 Peng
03-Jun-2021 09-Jun-2021 Zenkevich
10-Jun-2021 16-Jun-2021 Shukla
18-Jun-2021 23-Jun-2021 Arima/Hirschberger
24-Jun-2021 30-Jun-2021 Pfleiderer/Simeth
01-Jul-2021 07-Jul-2021 Vonka/Gerber
04-Aug-2021 05-Aug-2021 Commissioning/Technical Development
06-Aug-2021 11-Aug-2021 Toft-Petersen
13-Aug-2021 18-Aug-2021 Staub/Skoropata
20-Aug-2021 25-Aug-2021 McMorrow/Soh
26-Aug-2021 30-Aug-2021 Hatton/Moody
06-Sep-2021 09-Sep-2021 In-House Research
10-Sep-2021 15-Sep-2021 Hatton/Moody
17-Sep-2021 21-Sep-2021 Rahn
21-Sep-2021 22-Sep-2021 Commissioning/Technical Development
23-Sep-2021 29-Sep-2021 Janoschek/Simeth
01-Oct-2021 06-Oct-2021 Tolkiehn/Kaminski
07-Oct-2021 11-Oct-2021 Gupta
18-Oct-2021 21-Oct-2021 Reddy
21-Oct-2021 25-Oct-2021 In-House Research
25-Oct-2021 27-Oct-2021 Commissioning/Technical Development
28-Oct-2021 03-Nov-2021 Ronnow/Soh
04-Nov-2021 10-Nov-2021 Nandi/JANA
11-Nov-2021 17-Nov-2021 Frano Pereira/Vranas
22-Nov-2021 24-Nov-2021 In-House Research
25-Nov-2021 01-Dec-2021 White/Ukleev
02-Dec-2021 08-Dec-2021 Wende/Eggert
09-Dec-2021 13-Dec-2021 Hu
13-Dec-2021 15-Dec-2021 In-House Research
16-Dec-2021 22-Dec-2021 Keimer/Minola

Beamtime schedule for beamline P10


StartEnd 
15-Mar-2021 18-Mar-2021 Commissioning/Technical Development
18-Mar-2021 20-Mar-2021 In-House Research
20-Mar-2021 24-Mar-2021 Zhang/Begam
25-Mar-2021 27-Mar-2021 In-House Research
27-Mar-2021 02-Apr-2021 Lehmkuehler/Dallari
12-Apr-2021 15-Apr-2021 Commissioning/Technical Development
15-Apr-2021 26-Apr-2021 Salditt
26-Apr-2021 28-Apr-2021 In-House Research
29-Apr-2021 05-May-2021 Das/Perakis
06-May-2021 11-May-2021 Monaco/Martinelli
11-May-2021 17-May-2021 Ruta/Neuber
27-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 04-Jun-2021 Commissioning/Technical Development
04-Jun-2021 09-Jun-2021 Schreiber/Dax
10-Jun-2021 16-Jun-2021 Richard/Wu
17-Jun-2021 23-Jun-2021 Commissioning/Technical Development
24-Jun-2021 30-Jun-2021 In-House Research
01-Jul-2021 07-Jul-2021 In-House Research
04-Aug-2021 05-Aug-2021 Commissioning/Technical Development
05-Aug-2021 11-Aug-2021 Amann-Winkel/Li
12-Aug-2021 18-Aug-2021 Frano Pereira/Zaluzhnyy
19-Aug-2021 24-Aug-2021 shen/Blackburn
26-Aug-2021 30-Aug-2021 Steinrueck
08-Sep-2021 13-Sep-2021 Salditt
13-Sep-2021 20-Sep-2021 Salditt
23-Sep-2021 27-Sep-2021 Zhang/Begam
30-Sep-2021 04-Oct-2021 Schreiber/Zaluzhnyy
07-Oct-2021 11-Oct-2021 Richard/Dupraz
19-Oct-2021 23-Oct-2021 Basu
23-Oct-2021 27-Oct-2021 Basu
28-Oct-2021 31-Oct-2021 Roseker/Jo
04-Nov-2021 08-Nov-2021 Ruta
08-Nov-2021 13-Nov-2021 Lou
13-Nov-2021 17-Nov-2021 Monaco
25-Nov-2021 29-Nov-2021 Gutt/Timmermann
04-Dec-2021 08-Dec-2021 Richard/Dupraz
09-Dec-2021 15-Dec-2021 Kim
16-Dec-2021 22-Dec-2021 Kim

Beamtime schedule for beamline P11


StartEnd 
15-Mar-2021 18-Mar-2021 Commissioning/Technical Development
18-Mar-2021 18-Mar-2021 Industry
18-Mar-2021 19-Mar-2021 Education
19-Mar-2021 19-Mar-2021 Industry
19-Mar-2021 20-Mar-2021 Hehemann
20-Mar-2021 20-Mar-2021 Helmholtz Association Research
21-Mar-2021 22-Mar-2021 Wagner
22-Mar-2021 22-Mar-2021 Industry
22-Mar-2021 23-Mar-2021 Yefanov/Ivanova
23-Mar-2021 23-Mar-2021 Wagner
23-Mar-2021 23-Mar-2021 Industry
23-Mar-2021 23-Mar-2021 Commissioning/Technical Development
25-Mar-2021 30-Mar-2021 Chapman/Oberthuer
30-Mar-2021 30-Mar-2021 Commissioning/Technical Development
30-Mar-2021 31-Mar-2021 Hoebartner
31-Mar-2021 31-Mar-2021 Helmholtz Association Research
31-Mar-2021 01-Apr-2021 Helmholtz Association Research
01-Apr-2021 02-Apr-2021 Bochtler/Nowotny
12-Apr-2021 12-Apr-2021 Commissioning/Technical Development
12-Apr-2021 13-Apr-2021 Chapman/Sprenger
13-Apr-2021 13-Apr-2021 Hehemann
13-Apr-2021 13-Apr-2021 Short-term
13-Apr-2021 14-Apr-2021 Grudnik/Zak
14-Apr-2021 15-Apr-2021 Meents/Guenther
15-Apr-2021 15-Apr-2021 Industry
15-Apr-2021 16-Apr-2021 Clever/Holstein
16-Apr-2021 16-Apr-2021 Helmholtz Association Research
16-Apr-2021 17-Apr-2021 Keller/Winkler
17-Apr-2021 18-Apr-2021 Beck/Ruetten
18-Apr-2021 19-Apr-2021 Chapman/Sprenger
19-Apr-2021 19-Apr-2021 Groves
19-Apr-2021 19-Apr-2021 Short-term
19-Apr-2021 20-Apr-2021 Short-term
20-Apr-2021 20-Apr-2021 Industry
20-Apr-2021 21-Apr-2021 Kursula
21-Apr-2021 21-Apr-2021 Commissioning/Technical Development
22-Apr-2021 26-Apr-2021 Meents/Lieske
26-Apr-2021 26-Apr-2021 Commissioning/Technical Development
26-Apr-2021 27-Apr-2021 Sondermann
27-Apr-2021 27-Apr-2021 Helmholtz Association Research
27-Apr-2021 27-Apr-2021 In-House Research
27-Apr-2021 28-Apr-2021 Techert/Velazquez Garcia
28-Apr-2021 28-Apr-2021 Techert/Basuroy
28-Apr-2021 29-Apr-2021 Max-Planck-Society Research
29-Apr-2021 29-Apr-2021 Commissioning/Technical Development
29-Apr-2021 30-Apr-2021 Industry
30-Apr-2021 30-Apr-2021 Helmholtz Association Research
30-Apr-2021 01-May-2021 Helmholtz Association Research
01-May-2021 02-May-2021 Yefanov/Ivanova
02-May-2021 04-May-2021 Meents/Guenther
04-May-2021 05-May-2021 Cossar/Ottmann
06-May-2021 07-May-2021 Industry
07-May-2021 08-May-2021 Commissioning/Technical Development
08-May-2021 08-May-2021 Short-term
08-May-2021 09-May-2021 Span
09-May-2021 10-May-2021 Hoebartner
10-May-2021 11-May-2021 Keller
11-May-2021 11-May-2021 Helmholtz Association Research
11-May-2021 12-May-2021 Helmholtz Association Research
12-May-2021 12-May-2021 Industry
12-May-2021 13-May-2021 Grudnik/Zak
13-May-2021 14-May-2021 Chapman/Sprenger
14-May-2021 14-May-2021 In-House Research
14-May-2021 15-May-2021 Wagner
15-May-2021 16-May-2021 Meents/Guenther
16-May-2021 17-May-2021 Beck/Ruetten
27-May-2021 27-May-2021 Commissioning/Technical Development
27-May-2021 28-May-2021 Helmholtz Association Research
28-May-2021 28-May-2021 Short-term
28-May-2021 28-May-2021 Industry
28-May-2021 29-May-2021 Perbandt/Betzel
29-May-2021 29-May-2021 In-House Research
29-May-2021 30-May-2021 Sondermann
30-May-2021 31-May-2021 Bochtler/Nowotny
31-May-2021 31-May-2021 Helmholtz Association Research
31-May-2021 01-Jun-2021 Helmholtz Association Research
01-Jun-2021 01-Jun-2021 University Research (P11)
01-Jun-2021 02-Jun-2021 Techert/Basuroy
03-Jun-2021 03-Jun-2021 Industry
03-Jun-2021 04-Jun-2021 Grudnik/Zak
04-Jun-2021 04-Jun-2021 Commissioning/Technical Development
04-Jun-2021 05-Jun-2021 Commissioning/Technical Development
05-Jun-2021 05-Jun-2021 Helmholtz Association Research
05-Jun-2021 05-Jun-2021 Clever/Holstein
05-Jun-2021 06-Jun-2021 Short-term
06-Jun-2021 07-Jun-2021 Hoebartner
07-Jun-2021 08-Jun-2021 Royant
08-Jun-2021 12-Jun-2021 Oberthuer/Perbandt
12-Jun-2021 13-Jun-2021 Chapman/Sprenger
13-Jun-2021 14-Jun-2021 Beck/Ruetten
14-Jun-2021 14-Jun-2021 Commissioning/Technical Development
15-Jun-2021 15-Jun-2021 Helmholtz Association Research
15-Jun-2021 16-Jun-2021 Techert/Velazquez Garcia
17-Jun-2021 19-Jun-2021 Meents/Guenther
20-Jun-2021 21-Jun-2021 Short-term
21-Jun-2021 21-Jun-2021 In-House Research
21-Jun-2021 22-Jun-2021 Yefanov/Ivanova
22-Jun-2021 22-Jun-2021 University Research (P11)
22-Jun-2021 23-Jun-2021 Yefanov/Ivanova
23-Jun-2021 23-Jun-2021 Groves
24-Jun-2021 29-Jun-2021 Li/Chapman
29-Jun-2021 30-Jun-2021 Commissioning/Technical Development
01-Jul-2021 01-Jul-2021 In-House Research
02-Jul-2021 04-Jul-2021 Meents/Lieske
04-Jul-2021 05-Jul-2021 Kursula
05-Jul-2021 05-Jul-2021 In-House Research
05-Jul-2021 06-Jul-2021 Keller
06-Jul-2021 06-Jul-2021 Short-term
06-Jul-2021 06-Jul-2021 In-House Research
06-Jul-2021 07-Jul-2021 Helmholtz Association Research
04-Aug-2021 06-Aug-2021 Commissioning/Technical Development
06-Aug-2021 07-Aug-2021 Helmholtz Association Research
08-Aug-2021 09-Aug-2021 Hoebartner
09-Aug-2021 09-Aug-2021 Hehemann
09-Aug-2021 10-Aug-2021 Cossar/Ottmann
10-Aug-2021 11-Aug-2021 Groves
13-Aug-2021 14-Aug-2021 Beck/Ruetten
14-Aug-2021 15-Aug-2021 Meents/Guenther
15-Aug-2021 16-Aug-2021 Perbandt/Betzel
16-Aug-2021 17-Aug-2021 Kursula
18-Aug-2021 18-Aug-2021 Chapman/Sprenger
19-Aug-2021 20-Aug-2021 Sondermann
20-Aug-2021 21-Aug-2021 Chapman/Kremling
22-Aug-2021 23-Aug-2021 Yefanov
23-Aug-2021 23-Aug-2021 Helmholtz Association Research
25-Aug-2021 25-Aug-2021 Yefanov/Ivanova
26-Aug-2021 27-Aug-2021 Cossar/Ottmann
29-Aug-2021 30-Aug-2021 Span
07-Sep-2021 07-Sep-2021 Helmholtz Association Research
07-Sep-2021 08-Sep-2021 Helmholtz Association Research
08-Sep-2021 09-Sep-2021 Meents/Guenther
09-Sep-2021 10-Sep-2021 Chapman/Sprenger
10-Sep-2021 11-Sep-2021 Chapman/Kremling
21-Sep-2021 21-Sep-2021 Helmholtz Association Research
23-Sep-2021 24-Sep-2021 Clever/Holstein
25-Sep-2021 26-Sep-2021 Groves
26-Sep-2021 27-Sep-2021 Yefanov
27-Sep-2021 28-Sep-2021 Hehemann
30-Sep-2021 01-Oct-2021 Techert/Velazquez Garcia
01-Oct-2021 02-Oct-2021 Lane
02-Oct-2021 03-Oct-2021 Perbandt
04-Oct-2021 05-Oct-2021 Meents/Guenther
07-Oct-2021 07-Oct-2021 Helmholtz Association Research
10-Oct-2021 11-Oct-2021 Chapman/Sprenger
19-Oct-2021 19-Oct-2021 Helmholtz Association Research
20-Oct-2021 21-Oct-2021 Chapman/Kremling
21-Oct-2021 22-Oct-2021 Sondermann
24-Oct-2021 25-Oct-2021 Ponce-Salvatierra/Bujnicki
25-Oct-2021 26-Oct-2021 Beck/Ruetten
26-Oct-2021 27-Oct-2021 Groves
30-Oct-2021 31-Oct-2021 Perbandt
31-Oct-2021 01-Nov-2021 Yefanov
02-Nov-2021 02-Nov-2021 Helmholtz Association Research
02-Nov-2021 03-Nov-2021 Helmholtz Association Research
04-Nov-2021 05-Nov-2021 Cossar/Ottmann
05-Nov-2021 06-Nov-2021 Chapman/Sprenger
08-Nov-2021 10-Nov-2021 Lane
10-Nov-2021 10-Nov-2021 Chapman/Sprenger
11-Nov-2021 12-Nov-2021 Virovets/Scheer
12-Nov-2021 13-Nov-2021 Meents/Guenther
13-Nov-2021 14-Nov-2021 Beck/Ruetten
15-Nov-2021 15-Nov-2021 Helmholtz Association Research
24-Nov-2021 25-Nov-2021 Clever/Holstein
25-Nov-2021 26-Nov-2021 Chapman/Kremling
29-Nov-2021 29-Nov-2021 Helmholtz Association Research
02-Dec-2021 03-Dec-2021 Ponce-Salvatierra/Bujnicki
03-Dec-2021 04-Dec-2021 Chapman/Kremling
04-Dec-2021 05-Dec-2021 Meents/Guenther
06-Dec-2021 07-Dec-2021 Hehemann
13-Dec-2021 14-Dec-2021 Royant
17-Dec-2021 18-Dec-2021 Chapman/Sprenger
18-Dec-2021 19-Dec-2021 Beck/Ruetten
19-Dec-2021 20-Dec-2021 Groves
20-Dec-2021 20-Dec-2021 Helmholtz Association Research
20-Dec-2021 21-Dec-2021 Helmholtz Association Research
21-Dec-2021 22-Dec-2021 Virovets/Scheer

Beamtime schedule for beamline P21.1


StartEnd 
18-Mar-2021 22-Mar-2021 Bedford
23-Mar-2021 23-Mar-2021 In-House Research
25-Mar-2021 29-Mar-2021 Winkler
29-Mar-2021 02-Apr-2021 In-House Research
14-Apr-2021 19-Apr-2021 Brummerstedt Iversen/Raboel Joergensen
19-Apr-2021 21-Apr-2021 Lane/Vetter
22-Apr-2021 22-Apr-2021 In-House Research
03-May-2021 04-May-2021 In-House Research
06-May-2021 10-May-2021 Schneider/Poellmann
10-May-2021 14-May-2021 Morgenroth
27-May-2021 28-May-2021 In-House Research
02-Jun-2021 02-Jun-2021 In-House Research
02-Jun-2021 02-Jun-2021 In-House Research
02-Jun-2021 02-Jun-2021 In-House Research
03-Jun-2021 09-Jun-2021 Chang/Kuespert
10-Jun-2021 14-Jun-2021 Terraschke/Stroeh
14-Jun-2021 16-Jun-2021 In-House Research
17-Jun-2021 21-Jun-2021 Caupin/Lehmkuehler
21-Jun-2021 23-Jun-2021 Visser
23-Jun-2021 23-Jun-2021 In-House Research
24-Jun-2021 30-Jun-2021 Janoschek/Chang
01-Jul-2021 07-Jul-2021 Hayden
04-Aug-2021 05-Aug-2021 Industry
05-Aug-2021 06-Aug-2021 Parak/Staufer
06-Aug-2021 11-Aug-2021 Brummerstedt Iversen/Raboel Joergensen
12-Aug-2021 18-Aug-2021 Mascotto
19-Aug-2021 23-Aug-2021 Busch/Neuber
23-Aug-2021 25-Aug-2021 Kirsch
26-Aug-2021 28-Aug-2021 Cooper/Mathiesen
23-Sep-2021 29-Sep-2021 Brummerstedt Iversen/Roelsgaard
30-Sep-2021 03-Oct-2021 Jensen/Aalling-Frederiksen
18-Oct-2021 22-Oct-2021 Terban
22-Oct-2021 26-Oct-2021 Koziej/Harouna-Mayer
28-Oct-2021 03-Nov-2021 Blackburn
04-Nov-2021 10-Nov-2021 Janoschek/Simutis
11-Nov-2021 15-Nov-2021 Toft-Petersen
24-Nov-2021 27-Nov-2021 Gutmann
27-Nov-2021 01-Dec-2021 Majumdar
02-Dec-2021 08-Dec-2021 Guguchia
09-Dec-2021 15-Dec-2021 McMorrow/Faure
16-Dec-2021 22-Dec-2021 Monney/Nicholson

Beamtime schedule for beamline P21.2


StartEnd 
15-Mar-2021 24-Mar-2021 In-House Research
25-Mar-2021 25-Mar-2021 Industry
25-Mar-2021 31-Mar-2021 In-House Research
12-Apr-2021 13-Apr-2021 Commissioning/Technical Development
13-Apr-2021 13-Apr-2021 Industry
13-Apr-2021 21-Apr-2021 In-House Research
22-Apr-2021 26-Apr-2021 In-House Research
26-Apr-2021 28-Apr-2021 Commissioning/Technical Development
28-Apr-2021 29-Apr-2021 In-House Research
29-Apr-2021 05-May-2021 Magnussen/Fuchs
05-May-2021 06-May-2021 Commissioning/Technical Development
06-May-2021 12-May-2021 Commissioning/Technical Development
12-May-2021 17-May-2021 Lundgren/Larsson
27-May-2021 31-May-2021 In-House Research
31-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 09-Jun-2021 Commissioning/Technical Development
10-Jun-2021 14-Jun-2021 Schueltke
14-Jun-2021 16-Jun-2021 In-House Research
17-Jun-2021 21-Jun-2021 Fisk
21-Jun-2021 23-Jun-2021 Commissioning/Technical Development
24-Jun-2021 30-Jun-2021 Preuss/KOC
01-Jul-2021 05-Jul-2021 Talyzin
05-Jul-2021 07-Jul-2021 Karlsson
04-Aug-2021 07-Aug-2021 Commissioning/Technical Development
07-Aug-2021 11-Aug-2021 Fan/Xia
12-Aug-2021 18-Aug-2021 Zhu
19-Aug-2021 24-Aug-2021 Nilsson/Shipilin
27-Aug-2021 30-Aug-2021 Shen/Jiang
06-Sep-2021 09-Sep-2021 Schueltke
16-Sep-2021 21-Sep-2021 Oernek
23-Sep-2021 27-Sep-2021 Senyshyn
30-Sep-2021 06-Oct-2021 Schenk
07-Oct-2021 11-Oct-2021 Frankel/Thomas
21-Oct-2021 27-Oct-2021 Lundgren
28-Oct-2021 02-Nov-2021 Fisk
04-Nov-2021 09-Nov-2021 Reiser/Perakis
11-Nov-2021 16-Nov-2021 Upadhyay
22-Nov-2021 24-Nov-2021 Gallino/Riegler
24-Nov-2021 27-Nov-2021 Busch/Gallino
27-Nov-2021 30-Nov-2021 Yang
02-Dec-2021 08-Dec-2021 Gustafson
09-Dec-2021 14-Dec-2021 Escudero-Escribano/Harlow
16-Dec-2021 22-Dec-2021 Amann-Winkel/Li

Beamtime schedule for beamline P22


StartEnd 
20-Mar-2021 27-Mar-2021 Amann/Nilsson
27-Mar-2021 02-Apr-2021 Nilsson/Shipilin
12-Apr-2021 16-Apr-2021 Middey
16-Apr-2021 18-Apr-2021 Konashuk
22-Apr-2021 28-Apr-2021 Regoutz
02-May-2021 05-May-2021 Dubourdieu/Maudet
06-May-2021 11-May-2021 Maiti
11-May-2021 14-May-2021 In-House Research
14-May-2021 17-May-2021 Filatova
27-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 06-Jun-2021 In-House Research
06-Jun-2021 12-Jun-2021 Das Sarma
12-Jun-2021 16-Jun-2021 Zenkevich
18-Jun-2021 23-Jun-2021 Nilsson/Goodwin
24-Jun-2021 28-Jun-2021 In-House Research
28-Jun-2021 03-Jul-2021 Yildiz/Rahman
03-Jul-2021 07-Jul-2021 In-House Research
04-Aug-2021 10-Aug-2021 Schoenhense/Elmers
12-Aug-2021 16-Aug-2021 Roy Barman
16-Aug-2021 18-Aug-2021 Nayak
06-Sep-2021 12-Sep-2021 Amann/Nilsson
12-Sep-2021 18-Sep-2021 Rameshan
18-Sep-2021 22-Sep-2021 Panaccione
23-Sep-2021 25-Sep-2021 Kohlstedt/Kolhatkar
25-Sep-2021 29-Sep-2021 Nilsson/Degerman
30-Sep-2021 05-Oct-2021 Ortega/Schiller
07-Oct-2021 11-Oct-2021 Regoutz
18-Oct-2021 24-Oct-2021 Schoenhense/Elmers
24-Oct-2021 30-Oct-2021 Schoenhense/Elmers
06-Nov-2021 10-Nov-2021 Gupta
11-Nov-2021 15-Nov-2021 Hoesch
22-Nov-2021 27-Nov-2021 Wiemann/Mueller
28-Nov-2021 01-Dec-2021 Tjeng/Severing
04-Dec-2021 08-Dec-2021 Topwal
09-Dec-2021 14-Dec-2021 Gray
16-Dec-2021 22-Dec-2021 Das Sarma

Beamtime schedule for beamline P23


StartEnd 
15-Mar-2021 18-Mar-2021 Serdechnova/Karlova
18-Mar-2021 24-Mar-2021 Zschornak/Weigel
25-Mar-2021 31-Mar-2021 Viswanatha
12-Apr-2021 16-Apr-2021 Koper
16-Apr-2021 19-Apr-2021 Stock/Terraschke
19-Apr-2021 24-Apr-2021 In-House Research
24-Apr-2021 28-Apr-2021 Commissioning/Technical Development
29-Apr-2021 03-May-2021 Commissioning/Technical Development
03-May-2021 10-May-2021 Commissioning/Technical Development
10-May-2021 17-May-2021 Noheda/Nukala
27-May-2021 30-May-2021 In-House Research
30-May-2021 04-Jun-2021 Commissioning/Technical Development
04-Jun-2021 09-Jun-2021 Kirm/Omelkov
10-Jun-2021 16-Jun-2021 Ovchinnikova/Kulikov
17-Jun-2021 21-Jun-2021 In-House Research
21-Jun-2021 26-Jun-2021 Commissioning/Technical Development
28-Jun-2021 30-Jun-2021 Ameloot/Arnauts
01-Jul-2021 07-Jul-2021 Hamann/Pretzsch
19-Aug-2021 23-Aug-2021 Schreiber/Merten
23-Aug-2021 30-Aug-2021 Gaal
06-Sep-2021 10-Sep-2021 Glebov/Grenzer
10-Sep-2021 15-Sep-2021 Blawert/Serdechnova
16-Sep-2021 22-Sep-2021 Magnussen/Tian
23-Sep-2021 27-Sep-2021 In-House Research
27-Sep-2021 01-Oct-2021 Commissioning/Technical Development
01-Oct-2021 06-Oct-2021 Gaal/Richter
07-Oct-2021 11-Oct-2021 Richter/Corley
18-Oct-2021 23-Oct-2021 Baumbach/Jakob
23-Oct-2021 27-Oct-2021 Serre/Dovgaliuk
28-Oct-2021 03-Nov-2021 Commissioning/Technical Development
04-Nov-2021 08-Nov-2021 Lippmann/Huber
08-Nov-2021 15-Nov-2021 Pacella/Bardelli
22-Nov-2021 26-Nov-2021 In-House Research
26-Nov-2021 29-Nov-2021 Lippmann
09-Dec-2021 15-Dec-2021 Vartaniants/Sturm
16-Dec-2021 22-Dec-2021 Maroun

Beamtime schedule for beamline P24


StartEnd 
15-Mar-2021 22-Mar-2021 Commissioning/Technical Development
22-Mar-2021 24-Mar-2021 Virovets/Scheer
25-Mar-2021 30-Mar-2021 Van Smaalen
30-Mar-2021 30-Mar-2021 Commissioning/Technical Development
30-Mar-2021 31-Mar-2021 Techert/Thekku Veedu
31-Mar-2021 02-Apr-2021 Max-Planck-Society Research
12-Apr-2021 15-Apr-2021 Roehlsberger/Schmitt
15-Apr-2021 19-Apr-2021 Roehlsberger/Schulze
19-Apr-2021 21-Apr-2021 Englert
22-Apr-2021 27-Apr-2021 Park
27-Apr-2021 03-May-2021 Freudenberg/Glaser
03-May-2021 05-May-2021 Max-Planck-Society Research
06-May-2021 11-May-2021 Blackburn/shen
11-May-2021 12-May-2021 Commissioning/Technical Development
12-May-2021 17-May-2021 Noohinejad
27-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 09-Jun-2021 Shukla
10-Jun-2021 15-Jun-2021 Hayden
15-Jun-2021 18-Jun-2021 Max-Planck-Society Research
18-Jun-2021 20-Jun-2021 Malcherek
21-Jun-2021 25-Jun-2021 In-House Research
25-Jun-2021 28-Jun-2021 Virovets/Scheer
28-Jun-2021 02-Jul-2021 Visser
02-Jul-2021 07-Jul-2021 Van Smaalen
04-Aug-2021 09-Aug-2021 Commissioning/Technical Development
09-Aug-2021 13-Aug-2021 Athinarayanan
13-Aug-2021 18-Aug-2021 Mondal
19-Aug-2021 22-Aug-2021 Ruschewitz/Sebastian
24-Aug-2021 30-Aug-2021 Max-Planck-Society Research
06-Sep-2021 08-Sep-2021 Visser
08-Sep-2021 13-Sep-2021 Oeckler/Grauer
13-Sep-2021 15-Sep-2021 Malcherek
15-Sep-2021 17-Sep-2021 Shen
17-Sep-2021 22-Sep-2021 Hayden
23-Sep-2021 24-Sep-2021 Commissioning/Technical Development
24-Sep-2021 29-Sep-2021 In-House Research
30-Sep-2021 02-Oct-2021 Dey
02-Oct-2021 04-Oct-2021 Dey
04-Oct-2021 08-Oct-2021 Stachowicz
08-Oct-2021 11-Oct-2021 Neetika/shahed
18-Oct-2021 19-Oct-2021 Commissioning/Technical Development
19-Oct-2021 22-Oct-2021 Virovets/Scheer
22-Oct-2021 25-Oct-2021 In-House Research
25-Oct-2021 27-Oct-2021 Hoesch
28-Oct-2021 01-Nov-2021 Rekis
01-Nov-2021 05-Nov-2021 Upadhyay
05-Nov-2021 10-Nov-2021 Shukla
10-Nov-2021 12-Nov-2021 Shukla
12-Nov-2021 15-Nov-2021 Friese/Hakala
15-Nov-2021 17-Nov-2021 Englert
22-Nov-2021 23-Nov-2021 Education
23-Nov-2021 29-Nov-2021 Roehlsberger/Schulze
29-Nov-2021 02-Dec-2021 In-House Research
02-Dec-2021 07-Dec-2021 Van Smaalen
07-Dec-2021 08-Dec-2021 Commissioning/Technical Development
08-Dec-2021 13-Dec-2021 Oeckler
13-Dec-2021 15-Dec-2021 Dey
16-Dec-2021 22-Dec-2021 Karmakar

Beamtime schedule for beamline P61


StartEnd 
15-Mar-2021 02-Apr-2021 Commissioning/Technical Development
12-Apr-2021 16-Apr-2021 Schueltke
19-Apr-2021 20-Apr-2021 Pietsch/Shokr
22-Apr-2021 28-Apr-2021 Staron/Abreu Faria
29-Apr-2021 05-May-2021 Niendorf/Liehr
06-May-2021 10-May-2021 Katsura
13-May-2021 17-May-2021 Riedel/Li
27-May-2021 01-Jun-2021 Lathe
03-Jun-2021 08-Jun-2021 Schnick/Ambach
10-Jun-2021 13-Jun-2021 Oliveira
13-Jun-2021 16-Jun-2021 Schlenz/Gizer
17-Jun-2021 23-Jun-2021 Geandier
24-Jun-2021 28-Jun-2021 Gibmeier
28-Jun-2021 30-Jun-2021 Evans
01-Jul-2021 03-Jul-2021 Niendorf/Liehr
03-Jul-2021 07-Jul-2021 Gargioni
04-Aug-2021 08-Aug-2021 Kloss
08-Aug-2021 13-Aug-2021 Skokov
16-Aug-2021 18-Aug-2021 Mellin/Maimaitiyili
19-Aug-2021 22-Aug-2021 Kashaev/Sala
22-Aug-2021 25-Aug-2021 Kashaev/Kuliiev
26-Aug-2021 30-Aug-2021 Commissioning/Technical Development
09-Sep-2021 11-Sep-2021 Oliveira
11-Sep-2021 15-Sep-2021 Gibmeier
16-Sep-2021 21-Sep-2021 Neri
23-Sep-2021 27-Sep-2021 Haeussermann/Spektor
27-Sep-2021 03-Oct-2021 Farla/Ma
04-Oct-2021 09-Oct-2021 Katsura
18-Oct-2021 24-Oct-2021 Commissioning/Technical Development
24-Oct-2021 27-Oct-2021 Niendorf/Liehr
30-Oct-2021 31-Oct-2021 Schueltke
01-Nov-2021 03-Nov-2021 Gargioni
04-Nov-2021 07-Nov-2021 Athinarayanan/Shanbhag
08-Nov-2021 14-Nov-2021 Koch-Mueller/Sieber
15-Nov-2021 17-Nov-2021 Sun
22-Nov-2021 26-Nov-2021 Haeussermann
26-Nov-2021 01-Dec-2021 Frost/Man
02-Dec-2021 07-Dec-2021 Katsura
11-Dec-2021 15-Dec-2021 Reisgen/Akyel
18-Dec-2021 22-Dec-2021 Schueltke

Beamtime schedule for beamline P62


StartEnd 
01-Oct-2021 04-Oct-2021 Coelho Conceicao
07-Oct-2021 11-Oct-2021 Sun
18-Oct-2021 20-Oct-2021 Sanchez Cano/Parak
21-Oct-2021 26-Oct-2021 Lechner
28-Oct-2021 03-Nov-2021 Mascotto
04-Nov-2021 06-Nov-2021 Kaszkur/Hoell
06-Nov-2021 13-Nov-2021 Ramos-Gomes/Coelho Conceicao
13-Nov-2021 17-Nov-2021 Sanchez Cano
22-Nov-2021 25-Nov-2021 Balaguer/Solis
26-Nov-2021 29-Nov-2021 Stoica
29-Nov-2021 01-Dec-2021 Beck
03-Dec-2021 06-Dec-2021 Nickel
06-Dec-2021 08-Dec-2021 Balaguer/Solis
09-Dec-2021 13-Dec-2021 Hoell
13-Dec-2021 15-Dec-2021 Sun
16-Dec-2021 17-Dec-2021 Lips/Gericke
17-Dec-2021 20-Dec-2021 Liebi

Beamtime schedule for beamline P64


StartEnd 
15-Mar-2021 18-Mar-2021 Commissioning/Technical Development
18-Mar-2021 24-Mar-2021 Luetzenkirchen-Hecht
26-Mar-2021 26-Mar-2021 Industry
29-Mar-2021 01-Apr-2021 Koivula
12-Apr-2021 16-Apr-2021 Spiekermann
16-Apr-2021 20-Apr-2021 In-House Research
22-Apr-2021 26-Apr-2021 Grunwaldt/Doronkin
27-Apr-2021 03-May-2021 Bauer/Burkhardt
04-May-2021 10-May-2021 Bakradze
10-May-2021 10-May-2021 Industry
12-May-2021 16-May-2021 Canton
27-May-2021 02-Jun-2021 Shukla
03-Jun-2021 07-Jun-2021 Loges
07-Jun-2021 09-Jun-2021 Commissioning/Technical Development
10-Jun-2021 14-Jun-2021 Mascotto
14-Jun-2021 14-Jun-2021 Industry
15-Jun-2021 22-Jun-2021 Merte
22-Jun-2021 28-Jun-2021 Timoshenko
28-Jun-2021 02-Jul-2021 Viswanatha
02-Jul-2021 07-Jul-2021 Bandyopadhyay
04-Aug-2021 10-Aug-2021 Ruebhausen/Grimm-Lebsanft
10-Aug-2021 13-Aug-2021 John
13-Aug-2021 18-Aug-2021 Gautam
19-Aug-2021 23-Aug-2021 Knapp/Hua
24-Aug-2021 25-Aug-2021 Koziej/Kopula Kesavan
16-Sep-2021 19-Sep-2021 Kathyola/Schroeder
20-Sep-2021 22-Sep-2021 Koziej/Kopula Kesavan
23-Sep-2021 27-Sep-2021 Bauer/Wendholt
27-Sep-2021 29-Sep-2021 Bakradze
30-Sep-2021 04-Oct-2021 Koroidov
07-Oct-2021 11-Oct-2021 Bauer/Nowakowski
19-Oct-2021 25-Oct-2021 Ruebhausen/Grimm-Lebsanft
25-Oct-2021 29-Oct-2021 Bhattacharyya
29-Oct-2021 02-Nov-2021 Jentys
04-Nov-2021 10-Nov-2021 Haumann
11-Nov-2021 15-Nov-2021 Mascotto
15-Nov-2021 17-Nov-2021 Lukatskaya/Wee
23-Nov-2021 29-Nov-2021 Luetzenkirchen-Hecht
29-Nov-2021 03-Dec-2021 Gupta
03-Dec-2021 10-Dec-2021 Chirambatte Peter
10-Dec-2021 13-Dec-2021 Karmakar
13-Dec-2021 15-Dec-2021 Viswanatha
16-Dec-2021 21-Dec-2021 Gautam

Beamtime schedule for beamline P65


StartEnd 
15-Mar-2021 19-Mar-2021 Grunwaldt/Casapu
19-Mar-2021 23-Mar-2021 DeBeer/Joseph
25-Mar-2021 29-Mar-2021 Knapp/Fu
29-Mar-2021 02-Apr-2021 Mikhailova/Omar
12-Apr-2021 16-Apr-2021 Levard
23-Apr-2021 26-Apr-2021 Comba/Baur
27-Apr-2021 29-Apr-2021 Mikutta
30-Apr-2021 03-May-2021 Oeckler/Lindemann
03-May-2021 07-May-2021 Boubnov/Czioska
07-May-2021 12-May-2021 In-House Research
12-May-2021 17-May-2021 Bauer/Wendholt
27-May-2021 28-May-2021 Roth/Lobo
28-May-2021 02-Jun-2021 In-House Research
03-Jun-2021 08-Jun-2021 Grunwaldt/Sarma
10-Jun-2021 14-Jun-2021 Mueller
14-Jun-2021 18-Jun-2021 Schnohr
18-Jun-2021 21-Jun-2021 Kleist
01-Jul-2021 07-Jul-2021 Schnohr
04-Aug-2021 10-Aug-2021 Jentys
13-Aug-2021 17-Aug-2021 Santra
20-Aug-2021 23-Aug-2021 Schnohr
26-Aug-2021 30-Aug-2021 Mikhailova/Omar
06-Sep-2021 09-Sep-2021 Bauer/Nowakowski
16-Sep-2021 17-Sep-2021 Roth/Lobo
17-Sep-2021 22-Sep-2021 Weckhuysen/Genz
23-Sep-2021 29-Sep-2021 Borchert
01-Oct-2021 04-Oct-2021 Kuzmin
04-Oct-2021 06-Oct-2021 Couasnon/Desmau
07-Oct-2021 11-Oct-2021 Clemens/Schoch
18-Oct-2021 20-Oct-2021 Benedetti/QIN
20-Oct-2021 25-Oct-2021 Doronkin
28-Oct-2021 03-Nov-2021 Schnohr
04-Nov-2021 08-Nov-2021 DeBeer/Joseph
11-Nov-2021 17-Nov-2021 Grunwaldt
22-Nov-2021 26-Nov-2021 Timoshenko
26-Nov-2021 01-Dec-2021 Bakradze
02-Dec-2021 06-Dec-2021 Pudza
10-Dec-2021 14-Dec-2021 Priolkar
14-Dec-2021 17-Dec-2021 Senguttuvan
17-Dec-2021 22-Dec-2021 Singh